Posted June 06, 2011 Daily Report for Tuesday May 31, 2011

Continued excavation of Area 12; Reynolds installed 503' of 48" CIPP from SB10 to SB35;


Posted June 06, 2011 Daily Report for Sunday May 29, 2011

Maintained ditch pumps; Reynolds Inliner cut laterals for CIPP from SB7 to SB10;


Posted June 06, 2011 Daily Report for Saturday May 28, 2011

Maintained ditch pumps; Reynolds Inliner installed CIPP from SB7 to SB10;


Posted May 31, 2011 Daily Report for Friday May 27, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 48" CIPP installation from SB10 to SB7;


Posted May 31, 2011 Daily Report for Thursday May 26, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 36" CIPP installation from SB6 to SB7;


Posted May 31, 2011 Daily Report for Wednesday May 25, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 36" CIPP installation from SB6 to SB7;


Posted May 31, 2011 Daily Report for Tuesday May 24, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 21" CIPP installation from SB6 to SB3;


Posted May 31, 2011 Daily Report for Monday May 23, 2011

Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 21" CIPP installation from SB6 to SB3;


Posted May 24, 2011 Daily Report for Sunday May 22, 2011

Final grading and erosion controls at SWMU 6;


Posted May 24, 2011 Daily Report for Saturday May 21, 2011

Install culverts beneath 2nd St at B Ave;


Posted May 24, 2011 Daily Report for Friday May 20, 2011

Begin placement of vegetative cover at south half of CAMU;


Posted May 24, 2011 Daily Report for Thursday May 19, 2011

Continue final scraping/excavation of Cell 10 in EQB;


Posted May 21, 2011 Daily Report for Wednesday May 18, 2011

1/2 day due to heavy rain;


Posted May 21, 2011 Daily Report for Tuesday May 17, 2011

Excavate and remove south north 6" OWS pipe beneath SWMU 6 and plug\abandon pipe east of SWRP/EQB;


Posted May 21, 2011 Daily Report for Monday May 16, 2011

Clean south north 6" OWS pipe beneath SWMU 6 and east of SWRP/EQB;


Posted May 18, 2011 Daily Report for Saturday May 14, 2011

Excavated area south of SWMU 6 Area M along east fenceline of Marketing area;


Posted May 17, 2011 Daily Report for Friday May 13, 2011

Completed placement of sand cover on geosynthetics at south half of CAMU;


Posted May 17, 2011 Daily Report for Thursday May 12, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 17, 2011 Daily Report for Wednesday May 11, 2011

Begin Forms and backfill in AOC 1 for upcoming concrete pour;


Posted May 17, 2011 Daily Report for Tuesday May 10, 2011

Pre-Construction Meeting with Reynolds Inliner; Removed 6" OWS line beneath SWMU 5N;


Posted May 13, 2011 Daily Report for Monday May 9, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 13, 2011 Daily Report for Saturday May 7, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;


Posted May 13, 2011 Daily Report for Friday May 6, 2011

Collected post excavation samples from AOC 1, BCP, and SWMU 7 Cell 8;


Posted May 10, 2011 Daily Report for Thursday May 5, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44


Posted May 10, 2011 Daily Report for Wednesday May 4, 2011

Heavy rain; Limited Crew onsite to dewater and accept materials


Posted May 10, 2011 Daily Report for Tuesday May 3, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44


Posted May 10, 2011 Daily Report for Monday May 2, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU; Begin demolition/removal of SB44


Posted May 10, 2011 Daily Report for Sunday May 1, 2011

Continued placement of sand cover on geosynthetics at south half of CAMU;