Continued excavation of Area 12; Reynolds installed 503' of 48" CIPP from SB10 to SB35;
Maintained ditch pumps; Reynolds Inliner cut laterals for CIPP from SB7 to SB10;
Maintained ditch pumps; Reynolds Inliner installed CIPP from SB7 to SB10;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 48" CIPP installation from SB10 to SB7;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 36" CIPP installation from SB6 to SB7;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 36" CIPP installation from SB6 to SB7;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed 21" CIPP installation from SB6 to SB3;
Continue waste placement from SWMU 7 in north half of CAMU; Reynolds completed final CCTV and prepared for 21" CIPP installation from SB6 to SB3;
Final grading and erosion controls at SWMU 6;
Install culverts beneath 2nd St at B Ave;
Begin placement of vegetative cover at south half of CAMU;
Continue final scraping/excavation of Cell 10 in EQB;
1/2 day due to heavy rain;
Excavate and remove south north 6" OWS pipe beneath SWMU 6 and plug\abandon pipe east of SWRP/EQB;
Clean south north 6" OWS pipe beneath SWMU 6 and east of SWRP/EQB;
Excavated area south of SWMU 6 Area M along east fenceline of Marketing area;
Completed placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Begin Forms and backfill in AOC 1 for upcoming concrete pour;
Pre-Construction Meeting with Reynolds Inliner; Removed 6" OWS line beneath SWMU 5N;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Continued placement of sand cover on geosynthetics at south half of CAMU;
Collected post excavation samples from AOC 1, BCP, and SWMU 7 Cell 8;
Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44
Heavy rain; Limited Crew onsite to dewater and accept materials
Continued placement of sand cover on geosynthetics at south half of CAMU; Continue demolition/removal of SB44
Continued placement of sand cover on geosynthetics at south half of CAMU; Begin demolition/removal of SB44
Continued placement of sand cover on geosynthetics at south half of CAMU;