Posted March 3, 2011 Daily Report for Monday February 28, 2011

Continue excavation of SWMU 6 and AOC 1


Posted March 1, 2011 Daily Report for Saturday February 26, 2011

Began potholing and excavation of AOC 1


Posted March 1, 2011 Daily Report for Friday February 25, 2011

No excavation and/or hauling activities conducted; 1/2 day due to rain


Posted March 1, 2011 Daily Report for Thursday February 24, 2011

Continued SWMU 6 excavation and began east perimeter ditch of CAMU;


Posted March 1, 2011 Daily Report for Wednesday February 23, 2011

Continued SWMU 6 excavation and south perimeter ditch of CAMU;


Posted March 1, 2011 Daily Report for Tuesday February 22, 2011

Continued SWMU 6 excavation and south perimeter ditch of CAMU;


Posted March 1, 2011 Daily Report for Monday February 21, 2011

Continued SWMU 6 excavation and began excavating CAMU south perimeter ditch;


Posted February 23, 2011 Daily Report for Saturday February 19, 2011

Finish SWMU 10 excavtion;


Posted February 22, 2011 Daily Report for Friday February 18, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 22, 2011 Daily Report for Thursday February 17, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 22, 2011 Daily Report for Wednesday February 16, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 22, 2011 Daily Report for Tuesday February 15, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 16, 2011 Daily Report for Monday February 14, 2011

Continue Waste placement from SWMU 6 and SWMU 10;


Posted February 16, 2011 Daily Report for Saturday February 12, 2011

Continue Waste placement from SWMU 6; Resume excavation activities at SWMU 10


Posted February 16, 2011 Daily Report for Friday February 11, 2011

Continue Waste placement from SWMU 6; Begin installation of new fence at SWMU 6


Posted February 15, 2011 Daily Report for Thursday February 10, 2011

Limited day due to snow; 1/2 day of dewatering and decon activities;


Posted February 15, 2011 Daily Report for Wednesday February 9, 2011

Excavate and haul from SWMU 6; Begin addition of LKD to west section of EQB;


Posted February 15, 2011 Daily Report for Tuesday February 8, 2011

Excavate and haul from SWMU 6; Constructed access ramp from SWRP to CAMU;


Posted February 15, 2011 Daily Report for Monday February 7, 2011

Excavate and haul from SWMU 6 and SWMU 10 (severed power cable in SWMU 10; work ceased); Potholed outside SWMU 6 fenceline between BCP and Area M;


Posted February 9, 2011 Daily Report for Saturday February 5, 2011

No waste hauled to CAMU; 1/2 work day due to heavy rain;


Posted February 9, 2011 Daily Report for Friday February 4, 2011

Continued excavation and hauling out of SWMU 6


Posted February 8, 2011 Daily Report for Thursday February 3, 2011

Conducted potholing activities outside of fenceline at SWMU 6


Posted February 8, 2011 Daily Report for Wednesday February 2, 2011

Limited work due to rain; Dewatered work areas


Posted February 8, 2011 Daily Report for Tuesday February 1, 2011

Begin demolition of EQB concrete pump structure; Continue backfilling FBP and excavation at SWMU 6